ArticleCS - Article View

SAC-1982-07661

Published Sept. 26, 2018
Expiration date: 10/10/2018
The proposed work consists of reconfiguring an existing commercial marina to provide for additional floating dock space for transient boaters.  In detail, the applicant proposes to remove 6 finger docks on Dock A, remove 8 finger docks on Dock B, remove 4 finger docks on Dock E, remove 1 finger dock on Dock H, remove 1 finger dock on Dock I, install a 10’x165’ floating dock extension at the “T” head of Dock A, relocate the existing fuel dock 15’ shoreward, install 1,530’ of 10’ wide floating docks and associated anchor pilings immediately adjacent and parallel to the existing timber boardwalk and bulkhead, and construct a new gangway from the aforementioned floating dock to the fuel dock . The applicant has not proposed to mitigate for impacts to wetlands and/or waters of the United States, as the proposed activities only involve the installation of structures. The project purpose is to reconfigure an existing commercial marina to provide dockage for transient boaters.