The proposed work consists of the widening of a 2.4 miles segment of US 21 and approximately one mile of SC 51 to improve traffic safety, traffic efficiency to meet current design criteria and to improve stormwater drainage.  This project will include impact to a total of 635 linear feet of three separate tributaries and 0.1 acres of three separate wetland areas.  Specifically, this project will include placement of fill and piping in 469 linear feet of tributaries, placement of 166 linear feet of rock rip rap, placement of fill (including cut/fill) in 0.054 acres of wetlands and mechanical clearing of 0.045 acre of wetlands.