ArticleCS - Article View

SAC-2019-00781

USACE
Published July 24, 2023
Expiration date: 8/7/2023

The proposed work consists of of filling and raising a 2,500 LF portion of Big Bull Landing Road (a County maintained dirt road) to an approximate elevation of 15 feet (NAVD88) as well as the installation of three (3) additional 36-inch reinforced concrete pipes (RCP) to improve drainage. In addition, the proposed Bucksport Road Bypass Channel will include a relief ditch and 48-inch reinforced concrete pipe (RCP) that will outfall to the Waccamaw River. The proposed relief system will be located about 2,200 feet south of the Big Bull Landing Road. These proposed improvements will result in the deposition of fill material, clearing and minor excavation activities within wetland resources. The proposed construction activities associated with the raising of Big Bull Landing Road will consist of the deposition of 0.085 acres of fill within wetlands associated with an unnamed tributary to Cowford Swamp. The proposed roadbed improvements will also include the installation of three (3) additional 36-inch reinforced concrete pipes (RCP) to improve drainage. The construction activities associated with the proposed Bucksport Road Bypass Channel will result in 0.042 acres of clearing and 0.018 acres of wetland clearing/excavation.